Amenities include an indoor pool, on-site spa, multiple dining options, lobby gathering areas, fitness center, and flexible conference and special event spaces.
The grand staircase beckons guests to take advantage of sweeping views from multi-level landscaped deck and terrace areas overlooking Lake Washington.


Positioned steel trusses to clear span more than 100 feet in the large, open ballroom, supporting another smaller ballroom above as well as a large deck area that accommodates weddings and large convention events.
Closely coordinated with the cladding designer for support framing of a unique mix of cladding systems, including brick, precast, window wall, and metal paneling.


Future planning for the office towers required careful phasing, including coordination of a shared roadway and parking facilities that were operational before construction of the office towers was complete.
Successfully worked with the geotechnical team and the general contractor to mitigate poor soils by using geopier ground improvements to strengthen the soils and avoid deep pile foundations.
Facilitated early construction for site grading and geopiers by providing early grading and utility permit packages.
Stormwater design included the repurposing and use of an existing 200,000-gallon underground vault, a remnant of the former Shuffleton Steam Plant.